Work on the Beaminster Tunnel

For those of you keeping a watching eye on the Tunnel, the specialist team putting in the nails are working 11 day stints, then 2 days off. Drainage works continue, as do works on the tunnel portals. As of the beginning of last week 80 nails had gone in, and if you do pass by you will see that the team are often on ropes strung from the top of the slopes, it is a specialist job. I have had many requests for inclusion on the site visit and will get this organised as soon as possible.